A&P Mong Duong concrete factory exceeds the target

[02.08.2013 14:33]
View image
On September 27th, A&P Mong Duong Concrete Factory has exceeded the set target 5 hours when pouring 2.400 m3 of concrete for II Mong Duong Coal Thermal Power plant at Cam Pha town, Quang Ninh province in 15 hours (requirement by investors is 20 hours).



This is A&P biggest concrete forces mobilization ever. Mong Duong A&P concrete factory officials and staves have spared no efforts to fulfill their work, rapidly and punctually responding to investors’ requirements and ensuring A&P concrete quality.
The contract supplying concrete for project "II Mong Duong Coal Thermal Power Plant" was signed between A&P company and Doosan Vina from June 2011 (with a total investment value of 2.1 billion U.S dollars). The output that A&P company intends to supply is 300.000m3 during 4 years (from 2011 to 2015).
Some pictures



Image of A&P Concrete truck involved in pouring and pumping concrete at No.2 Mong Duong Coal Thermal Power Plant construction site – Quang Ninh province.






Share |

 Copy to print  Save file format  Send news via email



Other newsletters:



Up to the top

A&P GROUP - TẬP ĐOÀN A&P
Trụ sở:Số 73 Trung Kính - Trung Hòa - Cầu Giấy -Hà Nội
Tel:(084)3 836 2703 - Fax: (084)3 756 8820
Email:ap@apcorp.com.vn - Website: http://www.apcorp.com.vn
© Copyright 1996 - 2016 by A&P All rights reserved
® Bản quyền thuộc về apcorp.com.vn,Mọi tin bài đăng lại từ website này phải có sự chấp thuận bằng văn bản của A&P