At 7 am, 20 concrete cars of A & P Group (including 5 high capacity cars transporting concrete was first put into use) were gathered at A & P batch plant in Tien Son, Bac Ninh; which was ready for working. Campaign begins at 7h30 in the morning, lasting for 10 hours, with the continuous operation of the two batch plants with total capacity is 150m3 / h.

To carry out this campaign successfully , entire staff of Enterprise 2 - direct production unit – prepared with great care and closed coordination with other departments in an effort to meet the degree of utmost satisfaction of customer. In terms of materials, Vu Cong Uan (Director of Enterprise 2), said: "We had a meeting to assign works in detail, specific to each individual, each department and review all of the materials: cement, sand, petro ..., equipment, machine, technology chain and human in order to limit and control maximumly incidents can happen. "

Samsung (C & T and Everland) has long been a strategic partner of A & P Group, from the projects of constructing Samsung factory in periods in Yen Phong, Bac Ninh; to the project of constructing plants in Thai Nguyen and the project is now back to Samsung Display. In addition to quality, every Samsung’s partners are greatly pleased with the progress of supplying of goods of A & P Group. Concrete quality and the ability of supplying huge volume are strength of A & P.
Representatives of suppliers of materials for A & P Group said: "A & P always requires the best quality of materials. We have to be always greatly thoughtful, careful whenever supplying of goods for A & P. There were freight cars which transported to construction site which were returned if they didn’t meet the standards. Working with A & P, we also automatically improve our quality. "
Project of Samsung Display construction is expected to end in early 2015 with total investment is 1 billion USD.